Chapter 4 - Procurement Review

Introduction

Potential suppliers that believe that they may have been unfairly treated during a procurement solicitation covered by NAFTA, the AIT, the AGP, the CCFTA, the CPFTA or the CCOFTA may file a complaint with the Tribunal. The relevant provisions of the CITT Procurement Inquiry Regulations allow a complainant to first make an attempt to resolve the issue with the government institution responsible for the procurement before filing a complaint.

The Tribunal’s role is to determine whether the government institution followed the procurement procedures and other requirements specified in the applicable trade agreements.

When the Tribunal receives a complaint, it reviews it against the legislative criteria for filing. If there are deficiencies, the complainant is given an opportunity to correct them within the specified time limit. If the Tribunal decides to conduct an inquiry, the government institution is sent a formal notification of the complaint and a copy of the complaint itself. If the contract has been awarded, the government institution, in its acknowledgement of receipt of complaint letter, provides the Tribunal with the name and address of the contract awardee. The Tribunal then sends a notification of the complaint to the contract awardee as a possible interested party. An official notice of the complaint is published in the Canada Gazette. If the contract in question has not been awarded, the Tribunal may order the government institution to postpone the award of any contract pending the disposition of the complaint by the Tribunal.

After receipt of its copy of the complaint, the relevant government institution files a response called the Government Institution Report. The complainant and any intervener are sent a copy of the response and given an opportunity to submit comments. Any comments received are forwarded to the government institution and other parties to the inquiry.

Copies of any other submissions or reports prepared during the inquiry are also circulated to all parties for their comments. Once this phase of the inquiry is completed, the Tribunal reviews the information on the record and decides if a public hearing is necessary or if the case can be decided on the basis of the information on the record.

The Tribunal then determines whether or not the complaint is valid. If it is, the Tribunal may make recommendations for remedies, such as re-tendering, re-evaluating or providing compensation to the complainant. The government institution, as well as all other parties and interested persons, is notified of the Tribunal’s decision. Recommendations made by the Tribunal are, by statute, supposed to be implemented to the greatest extent possible. The Tribunal may also award reasonable costs to the complainant or the responding government institution depending on the nature and circumstances of the case.

Procurement Complaints

Summary of Activities
  2011-2012 2012-2013
Number of Procurement Cases Received

Carried over from previous fiscal year

4 3

Received in fiscal year

62 53
Total 66 56
Disposition—Complaints Accepted for Inquiry

Dismissed

1 1

Not valid

10 8

Valid or valid in part

1 1

Ceased

- 2

Withdrawn/abandoned

4 3
Subtotal 16 15
Disposition—Complaints Not Accepted for Inquiry

Lack of jurisdiction/not a potential supplier

7 2

Late filing

11 10

Not a designated contract/no reasonable indication of a breach/premature

28 25

Withdrawn/abandoned

1 2
Subtotal 47 39
Outstanding at End of Fiscal Year 3 2
Decisions to initiate 15 15
Remanded cases 4 -

In 2012-2013, the Department of Public Works and Government Services (PWGSC) issued approximately 11,503 contracts valued at between $25,000 and $2 billion each, for a total value of $7 billion. The 53 complaints that the Tribunal received in the fiscal year pertained to 50 different contracts with a collective value of over $350 million.

Summary of Selected Determinations

During the fiscal year, the Tribunal issued 52 decisions on whether to accept complaints for inquiry, which included one decision to inquire that was made in a matter received in the previous fiscal year, and 12 final decisions on complaints that were accepted for inquiry, for a total of 64 decisions. Two cases were still in progress at the end of the fiscal year.

Of the complaints investigated by the Tribunal in carrying out its procurement review functions, certain decisions stand out because of their legal significance. Brief summaries of a representative sample of these cases are included below. These summaries have been prepared for general information purposes only and are not intended to be of any legal value.

PR-2012-006—Secure Computing LLC

This complaint was filed by Secure Computing LLC (Secure Computing) concerning a procurement by PWGSC on behalf of the Department of National Defence (DND) for the provision of networking equipment. Secure Computing alleged that DND accepted products that were not compliant with the requirements of the solicitation.

PWGSC conceded that the units delivered by the winning bidder, Conexsys Communications Ltd. (Conexsys), did not meet the requirements. However, PWGSC submitted that, as the allegations contained in the complaint related to matters that fall under contract administration, an area which is beyond the Tribunal’s jurisdiction, and given that PWGSC had advised the Tribunal that it intended to enforce the terms of the contract and require Conexsys to deliver compliant products that meet all the requirements of the solicitation documents and of the contract, the Tribunal ought to dismiss this complaint.

The Tribunal found that PWGSC had evaluated Conexsys’ proposal, as it was submitted at the time of bid closing, in accordance with the terms of the solicitation documents. Accordingly, the decision to award the contract to Conexsys was reasonable because, on its face, Conexsys’ proposal was fully compliant with the technical requirements of the solicitation. The Tribunal was satisfied that PWGSC took the necessary steps to enforce the contract that was awarded to Conexsys and that this matter had to be treated as one of contract administration or contract performance over which the Tribunal does not have jurisdiction. Finally, the Tribunal did not accept Secure Computing’s argument that PWGSC’s actions in this matter improperly permitted Conexsys to repair its initial bid. Bid repair is a term used to describe the improper alteration or modification of a bid either by the bidder or by the procuring entity after the deadline for the receipt of bids has passed. In this case, there was no such alteration or modification of Conexsys’ bid. Therefore, the Tribunal determined that the complaint was not valid.

PR-2012-007—Sunny Jaura d.b.a. Jaura Enterprises

Sunny Jaura d.b.a. Jaura Enterprises (Jaura) filed a complaint concerning a procurement by PWGSC on behalf of DND for the provision of temporary housing accommodation services in Mesa, Arizona. According to Jaura, PWGSC and DND improperly determined that its proposal was non compliant with two mandatory technical requirements in the solicitation. After the Tribunal accepted the complaint for inquiry, PWGSC filed evidence that the estimated value of the contract was below the monetary thresholds specified in the trade agreements.

In this case, the Tribunal considered whether DND selected a valuation method with the intention of avoiding the obligations of the trade agreements. Although the value of the contract awarded to the winning bidder, Oakwood Temporary Housing, and the total amount of Jaura’s bid were both greater than the value of the contract as estimated by DND, this could have been attributable to the fact that PWGSC only received proposals from two bidders. In the end, the Tribunal was satisfied that the estimated value of the contract was not unreasonable. As the estimated value of the contract was below the monetary thresholds specified in the applicable trade agreements, the Tribunal found that the complaint did not relate to a “designated contract”. Accordingly, the Tribunal was without jurisdiction to conduct an inquiry, and the complaint was dismissed.

PR-2012-014—Weir Canada Inc.

Weir Canada Inc. (Weir) filed a complaint concerning a procurement by PWGSC on behalf of DND for the repair, overhaul and testing of a variety of pump assemblies or subassemblies used in various fluid systems on board DND ships. Weir alleged that PWGSC failed to conduct a fair and unbiased procurement process because the Request for Proposal (RFP) contained certain requirements that were unjustifiably biased in favour of particular Original Equipment Manufacturer (OEM) goods and OEM bidders, with the effect of excluding Weir’s bid. Specifically, Weir alleged that the following requirements under the RFP were unjustifiably biased in favour of OEM goods and OEM bidders: certification of the supply of OEM parts (Requirement No. 1); and the bidder must be an OEM or under a contract pertaining to technical data and repair/overhaul specifications with an OEM (Requirement No. 2).

The Tribunal found that a proper interpretation of section 6 of the CITT Procurement Inquiry Regulations that a complainant’s assumption regarding its ability to meet requirements which it finds objectionable was irrelevant. Once a complainant knows or ought to know the basis of its complaint, it should take action. Therefore, Weir should have reasonably objected or filed a complaint within 10 working days of May 31, 2012, the day on which the RFP was issued, and should not have waited to see if its subcontractor OEM, Curtiss-Wright, would agree to support its bid.

In any event, even if section 6 of the CITT Procurement Inquiry Regulations could be construed such that the relevant time line was when Weir knew that it could not meet the requirements of the RFP which it found objectionable, then Weir reasonably ought to have objected to PWGSC or filed a complaint with the Tribunal within 10 working days of July 6, 2012, when Curtiss-Wright responded to Weir that it would not be able to support its bid. That would make the objection to Requirement No. 2 late, considering that it was not made until August 22, 2012, and the complaint was not filed until September 4, 2012. Similarly, even though the objection with respect to Requirement No. 1 would have been timely, having been made on July 17, 2012, it was nonetheless late because there was a clear denial of relief to this objection on August 9, 2012, when PWGSC issued amendment No. 006, but the complaint was not filed until September 4, 2012. Therefore, the complaint was late on both grounds, and the Tribunal decided not to conduct an inquiry.

Disposition of Procurement Complaints
File No. Complainant Status/Decision
PR-2011-049 E.G. Spence Residential, Commercial and Industrial Maintenance and Construction Decision issued on April 2, 2012
Complaint valid
PR-2011-053 Service d’entretien JDH Inc. Complaint withdrawn on April 5, 2012
PR-2011-061 The Masha Krupp Translation Group Limited Decision issued on May 28, 2012
Complaint not valid
PR-2011-062 Secure Computing LLC Decision made on March 29, 2012
Complaint premature
PR-2012-001 Secure Computing LLC Decision made on April 11, 2012
No reasonable indication of a breach
PR-2012-002 ADRM Technology Consulting Group Corp./Randstad Interim Inc. Decision made on April 26, 2012
No reasonable indication of a breach
PR-2012-003 2127464 Ontario Inc. o/a Window Butler Decision made on May 10, 2012
Late filing
PR-2012-004 The Corporate Research Group Ltd. Decision made on May 10, 2012
Complaint premature
PR-2012-005 Accent on Clarity Decision made on June 13, 2012
No reasonable indication of a breach
PR-2012-006 Secure Computing LLC Decision issued on October 23, 2012
Complaint not valid
PR-2012-007 Sunny Jaura d.b.a. Jaura Enterprises Order issued September 5, 2012
Dismissed—lack of jurisdiction
PR-2012-008 Clearpath Robotics Inc. Complaint withdrawn on August 22, 2012
PR-2012-009 Ridgeline Mechanical Ltd. Decision made on July 17, 2012
No reasonable indication of a breach
PR-2012-010 Thales Canada Inc. Decision made on July 27, 2012
No reasonable indication of a breach
PR-2012-011 9198-6919 Québec Inc.  o/a Verreault Inc. Decision made on August 1, 2012
No reasonable indication of a breach
PR-2012-012 Samson & Associates Decision issued on October 19, 2012
Complaint not valid
PR-2012-013 Team Sunray and CAE Inc. Decision issued on October 25, 2012
Complaint not valid
PR-2012-014 Weir Canada Inc. Decision made on September 6, 2012
Late filing
PR-2012-015 Storeimage Decision issued on January 18, 2013
Complaint not valid
PR-2012-016 Professional Computer Consultants Group Ltd. (Procom) Decision issued on November 30, 2012
Complaint not valid
PR-2012-017 Headwall Photonics, Inc. Decision made on September 25, 2012
No reasonable indication of a breach
PR-2012-018 Mediamix Interactive Decision made on October 4, 2012
No reasonable indication of a breach
PR-2012-019 P.J.W. van Zyl and Sons Ltd. Decision made on October 5, 2012
No reasonable indication of a breach
PR-2012-020 C3 Polymeric Limited Decision issued on February 14, 2013
Complaint not valid
PR-2012-021 Paul Pollack Personnel Ltd. o/a The Pollack Group Canada Decision issued on January 11, 2013
Complaint not valid
PR-2012-022 Offshore Systems Ltd. Order issued on November 28, 2012
Inquiry ceased
PR-2012-023 Paul Pollack Personnel Ltd. o/a The Pollack Group Canada Complaint withdrawn on November 28, 2012
PR-2012-024 Gear Up Motors Order issued on November 26, 2012
Inquiry ceased
PR-2012-025 Central Automotive Inspections Records & Standards Services (CAIRSS) Corp. Decision made on October 31, 2012
No reasonable indication of a breach
PR-2012-026 Les Entreprises Prebbel Enterprises Inc. Decision made on November 5, 2012
Late filing
PR-2012-027 Star Group International Decision made on November 16, 2012
Complaint premature
PR-2012-028 Teledyne DALSA Inc. Decision made on November 29, 2012
No reasonable indication of a breach
PR-2012-029 Quality Control International in joint venture with Service Star Building Cleaning Decision made on November 30, 2012
No reasonable indication of a breach
PR-2012-030 Todd Dunnett Enterprises Decision made on December 6, 2012
Complaint premature
PR-2012-031 Tetra Tech WEI Inc. Decision made on December 5, 2012
Late filing
PR-2012-032 Primex Project Management Limited Decision made on December 12, 2012
Late filing
PR-2012-033 Napier-Reid Ltd. Decision made on December 11, 2012
No reasonable indication of a breach
PR-2012-034 Adlerhorst International, Inc. Decision made on December 18, 2012
Lack of jurisdiction
PR-2012-035 Mistral Security Inc. Accepted for inquiry—in progress
PR-2012-036 Rampart Aviation, LLC Decision made on January 7, 2013
Not a potential supplier
PR-2012-037 1760533 Ontario Ltd. o/a Sovereign Chauffeured Cars Decision made on January 7, 2013
Late filing
PR-2012-038 Flag Connection Inc. Decision made on January 9, 2013
No reasonable indication of a breach
PR-2012-039 The Ancien Group Inc. Decision made on January 28, 2013
Not a designated contract
PR-2012-040 Flag Connection Inc. Decision made on January 25, 2013
No reasonable indication of a breach
PR-2012-041 Professional Language School Decision made on February 1, 2013
No reasonable indication of a breach
PR-2012-042 Parsons Brinkerhoff Halsall Inc. d.b.a. Halsall Associates Complaint withdrawn on February 15, 2013
PR-2012-043 Sunny Jaura o/a Jaura Enterprises Decision made on February 21, 2013
No reasonable indication of a breach
PR-2012-044 ECI Networks Canada Decision made on March 7, 2013
Late filing
PR-2012-045 Flaman Management Partners Ltd. Decision made on March 6, 2013
Late filing
PR-2012-046 1091847 Ontario Ltd. Decision made on March 12, 2013
No reasonable indication of a breach
PR-2012-047 M.L. Wilson Management Accepted for inquiry—in progress
PR-2012-048 G4S Secure Solutions (Canada) Ltd. Complaint withdrawn on March 13, 2013
PR-2012-049 Manitex Liftking ULC Decision made on March 19, 2013
Late filing
PR-2012-050 Verreault Navigation Inc. Decision made on March 14, 2013
Complaint premature
PR-2012-051 Agri-SX Inc. Decision made on March 27, 2013
Late filing
PR-2012-052 Team Eagle Ltd. Decision made on March 19, 2013
Complaint premature
PR-2012-053 9178-6574 Québec Inc. dba Moment Factory Decision made on March 26, 2013
No reasonable indication of a breach

Judicial Review of Procurement Decisions

Decisions Appealed to the Federal Court of Appeal
File No. Complainant Before the Tribunal Applicant Before the Federal Court of Appeal Court File No./Status
Note: The Tribunal has made reasonable efforts to ensure that the information listed is complete. However, since the Tribunal usually does not participate in appeals to the Federal Court of Appeal or the Federal Court, it is unable to confirm that the list contains all appeals or decisions rendered that were before the Federal Court of Appeal and the Federal Court.
PR-2011-007 Acklands-Grainger Inc. Acklands-Grainger Inc. A—387—11
Application dismissed
(November 19, 2012)
PR-2011-031 Bell Canada Bell Canada A—397—11
Application dismissed
(May 29, 2012)
PR-2011-009 and PR-2011-010 The Access Information Agency Inc. The Access Information Agency Inc. A—419—11
Application dismissed
(September 11, 2012)
PR-2011-023 Almon Equipment Limited Almon Equipment Limited A—45—12
Application dismissed
(December 5, 2012)
PR-2011-022 Almon Equipment Limited Almon Equipment Limited A—46—12
Application dismissed
(December 5, 2012)
PR-2012-010 Thales Canada Inc. Thales Canada Inc. A—368—12
Application discontinued
(February 7, 2013)
PR-2012-014 Weir Canada Inc. Weir Canada Inc. A—430—12
Application dismissed
(February 6, 2013)
PR-2012-013 Team Sunray and CAE Inc. Team Sunray and CAE Inc. A—497—12
Application discontinued
(February 12, 2013)
PR-2012-015 Storeimage Storeimage A—66—13
In progress